Steve Palmier Architecture

Project Management Services for Telus Mobility, Burnaby, Canada
Interior Design Upgrade

Typical floor plan.....................................Completed interior............Entry stair....................Exterior.......................

The design program:
Called for the upgrade of approximately 100,00 sq ft of office space on 4 levels to include a variety of spaces: open plan office area with perimeter managers areas, privacy rooms, teaching areas, conference rooms and kitchenette.

The design also incorporated the following:
- Indirect up-lighting is retained and enhanced to minimise glare on the monitors.
- Audio-visual systems incorporated.
- Concrete structure is reused.
- Ceiling tiles, linear ceiling diffusers, and some light fixtures were reused.
- Existing mechanical system was retained and adjusted to suit the new layouts.
- Retaining men's and women's washrooms
- Whiteboards, projector screens were re-employed.
- Some office furniture was reused.
- Low VOC adhesives were specified for health reasons.
- Dust enclosure was used during construction activities.

Consultants:
Sizeland Evans Interior Design
Omicron (Mechanical, Electrical and Structural engineering)

Main Contractor:
Hodgson King + Marble


Philosophy |||| Awards |||| Projects |||| Practice Profile |||| Links |||| Green Design